Project Summary
We were happy to work with Milltol Ltd in supplying and installing a 83.52kWp capacity system to one of their industrial units at their premises in Rotherham.
Our install teams were on-site for a total of 10 days and fitted 192 panels to the existing corrugated roof. We used a 60kW Three Phase Solis inverter to power the system.
With the system live and running, we predict approximately 53,931kWh of electricity will be generated annually by solar alone.
Our install teams were on-site for a total of 10 days and fitted 192 panels to the existing corrugated roof. We used a 60kW Three Phase Solis inverter to power the system.
With the system live and running, we predict approximately 53,931kWh of electricity will be generated annually by solar alone.
System Installed
- x192 Jinko 435Watt Panels
- 60kW Solis S5 String Inverter
Estimated Cost Savings
We estimated an impressive £13,190 saving within the first year of Milltol Ltd's system going live (excluding VAT)